As part of the work to reduce road congestion, the construction of a 6-lane road linking Tolgoit Road with Ard Ayush Avenue / Central Trauma Hospital with "Sodon" Khoroolol is ongoing with funds from the capital's budget. The project includes 3.9 km of road with a 31 metre long bridge structure and five underpasses.
The general contractor of road construction is the joint venture of "Mongol Zam Group" LLC and "Ganburd" LLC, while our joint venture of "SRP Engineer Consulting Mongolia" LLC and "MIL” LLC provides consultancy services for daily construction supervision.
In the past, more than 360 units of land were relocated for the construction of the above-mentioned project. As of today, the bridge and retaining wall have been completed, and the earthwork is at about 70 percent.